|
DASR |
![]() |
Digital Air Surveillance Radar
(DASR) has become a nationwide requirement to replace the aging ASR-7 and 8 systems
in FAA and DOD air traffic facilities. Standard Terminal Automated Replacement
System (STARS), the new terminal updated hardware system, requires a digital radar feed to
drive the system. DASR systems will be installed in terminal air traffic facilities
not sited with ASR-9, the only existing terminal FAA digital radar (other
than the digitized ASR-8's). Some ASR-9
facilities will receive a back-up or a satellite airport ASR-11 system. |
HISTORY |
NATCA has been
very involved with the ASR-11 project. NATCA ASR-11 Reps, to date, have been Randy
Wadle (MIA), Richard Brent (SCK now at ORD) and Perry Doggrell (P31), who now serves in
that position. DOD has been the lead agency in the majority of ASR-11 negotiations.
In recent years, NATCA and the FAA have been very actively involved in
developments as the system had been experiencing numerous shortcomings and identified
problems not being adequately addressed.![]()
Dear Brothers and Sisters,
As you are no doubt aware, 100-plus FAA facilities have been identified to receive the
Raytheon DASR System 11 (ASR-11) replacement radar. There has not been much information
floating around concerning the ASR-11, and lots of questions. We asked Raytheon to
enlighten us on the entire preparation and installation process
they graciously sent
us a flow chart depicting the entire process for DASR installations. It was a very
extensive creation and quite large. We converted the flow chart into an outline mode and
the above link (ASR-11 Facility Process) will yield
the MS Word document.
The new mode of FAA technology replacement, involving NATCA and PASS with the FAA in all processes, has created a more harmonious relationship in the FAA equipment upgrade procedure. At the facility level, we must realize that there are certain items, in the installation, that will be site specific; however, most changes to the equipment installation cannot be changed without national (NATCA, PASS and FAA) approval. Approval for any changes would be held to the same stringent requirements applied to the system during development and the cost of these changes would have to be absorbed by the program (which is already taxed). Hopefully the ASR-11 Tech Rep Teams have covered or will cover most potential problems during OT&E and IOT&E and changes will not become an issue.
Locally (at ERI) FAA management, NATCA and PASS have worked together on the proposed ASR-11 install since the beginning. Raytheon and FAA HQ have answered all our questions and have been very accommodating in all areas to date. With more information being available at the facility, we hope this may make us more informed partners in the process that will be taking place.
Good luck,
Andy Chalot
NATCA ASR-11 Team
NATCA Safety Erie Tower
Achalay@csonline.net or natcaeri@velocity.net
ASR-11... STATUS |
Latest implementation waterfall for the ASR-11 came out on March 5th, but I am having problems getting the file.....
the last ASR-11 Waterfall on here is Feb 5, 2004.
LINK to ASR-11 Historical Events from 2001-2003
| Erie ASR-11 Radar Site |
November 4, 2004
Raytheon, FAA and local AF are still working the
issues that need cleaned up before we commission the ASR-11. A new ARTS
build should be here anyday and that should have every item cleaned up in the
automation arena. The radar performance is splendid; however, the weather
radar seems to be off from what other radar sources (NEXRAD, Doppler, airborne
radars) are showing. The ASR-11 weather radar shows only quantity of
precipitation in weather and the levels are graded by that amount. We have
had several thunderstorms pass through lately and the ASR-11 is only showing
level 1 and 2 weather activity.
October 4, 2004
We still have a few issues that need
rectified before we commission the ASR-11. The
commercial power, supplied by Penelec, has been a recurring problem as the feed
has been dropping almost daily and is consistently running about 10 volts low.
This condition causes the UPS to take over and then brings the EG (Engine
Generator) online to provide critical power to the radar until acceptable
commercial power is restored to the system.
Since August 16th, the ASR-11 EG has run over 65 hours.
Penelec has installed monitors at the site but will not talk to anyone
locally. This constant utilization
of the EG and UPS will have an effect on the lifespan of these
vital support pieces. Raytheon
is working the issue and hopes to work out a suitable remedy.
The control tower VDCU (Video Display Control Unit) is not currently backed up
by a UPS. Whenever there is a power
bump (surge or drop) the unit ceases working and a manual reset is required to
get it back in operation. The tower
VDCU controls the display of the ASR-11 weather and primary target selection.
The ARTS IIE MSAW and acquire/drop areas are slightly out of sync and are in the
progress of being amended with a new patch.
Raytheon had a new survey done and now everyone should be on the same
sheet of music.
September 1, 2004
The ORD period to date has gone quite
well. We have a few items that are being addressed. Weather radar
levels are off slightly and the ARTS IIE automation is being fine tuned.
Tweaking will continue until the system is like a Swiss-watch. Will keep
you all updated.
August 23, 2004
It has been a LONG time coming but I am
ecstatic to announce that the Erie DASR-11 commenced the Operational Readiness
Demonstration (ORD)at 6:00 AM this morning. Thanks to the dedication of a
large group of technicians and experts who worked endlessly throughout the
preceding weekend, this ORD date was struck!! Throughout the day, the
ASR-11 performed as advertised. The ORD will continue until controllers
and technicians are satisfied with the performance and recommend commissioning
the radar. This could transpire in 30 days depending on the radar.
August 17, 2004
On the early morning of August 12th, Erie Tower was a hotbed of activity.
The "Dry Run Cutover" test of the ERI ASR-11 was scheduled and went
exceptionally well. Also tested was the automation interface
-flawless. The CENRAP Switch worked as advertised. CENRAP Plus was
also tested an it also passed the muster. There is still much to be
completed before the ORD date of August 23rd. All Teams (FAA, Raytheon,
Contractors, FAA ANI Team and Airways Facilities (both SMO and local techs) are
putting out 110% trying to meet the August 23rd ORD date. We are all
sleeping with our fingers crossed to make this date happen.
August 6, 2004
Well we are about ready to "rock and
Roll" with the ASR-11. Most of the outstanding items have been fixed
or will be before going ORD. ORD date is planned for August 23.
Controller training is in progress. A dry-run cutover will take place
during the midnight shift on August 11-12.
June 12, 2004
The FAA ASR-11 Commissioning Flight
Evaluation took place June 8-9 with a KingAir 300 flying the run. Coverage
was excellent in all quadrants with the exception of the Jamestown, NY (JHW)
area and the coverage was much better than our curent ASR-7 provides but not
quite up to that observed by the FAA Optimization Team. The "flight
check" is performed with only 7 of 8 power amplifier modules and in the
Circular Polarization (CP) mode, so this may have had some bearing on the
results. Edge of scope is 59 NM and we observed the BE30 go off the scope
SW thru NW at 2,000 MSL. We lost the target at 16NM on the
ASR-7!!
Aylmer VOR (YQO) was 3,000. JARVS, MOAWK and BROTO intersections were
2,000. Dunkirk (DKK) was 3,000. JHW airport was 4,500 and the JHW
VOR was 5,000 MSL. Tiduote VOR (TDT) was 4,500 and Franklin VOR (FKL)
was 5,000. Corry-Lawrence airport (8G2) was 3,500 and Brokenstraw airport
(PA11) was 4,000 MSL. Port Meadville airport (GKJ) was 3,000...
LINES intersection was 2,500... CLERI intxn was 2,500. These altitudes
were our required altitudes and lower altitudes were not checked at this time so
coverage could and probably will be better than that attained in the flight
check.
The technician/evaluators were going out to the ASR-11 site to compile the results and see if there was anything that could be affecting the JHW area coverage other than the reduced power used for the evaluation.
May 31, 2004
Radar
coverage altitudes listed below (Primary Radar / Secondary Radar) were better
that requested and are projected to be as follows:
ERI
Arpt - 700/800
JFN/HZY - 1200/1300
8G2 Arpt - 2300/2600
The
FAA AOS optimization was conducted during a rash of inclement weather, so the
final coverage numbers could end up being better than those reported.
The
only problem encountered during optimization was one that has existed for some
time = false plots and false tracks along the outer edge of weather and along
the edges of the different weather levels. The ASR-11 has a "velocity editor" which eliminates
primary targets less than 40kts airspeed. The
AOS Team upped the speed to 60 kts and the situation was vastly improved;
however, we have a problem with increasing to this speed.
We do have non-transponder aircraft that frequent ERI that will be edited
out due to low performance (60 kts or less) and when the wind is strong on
final. Some of these targets
produced by this weather edge phenomena are high-confidence targets and will
give us a "diamond" on the ARTS which indicates a primary target.
This problem is indemic to the system and is being worked on by Raytheon.
May 27, 2004
The FAA Optimization Team finished
optimizing the ERI ASR-11 and radar coverage figures were given at the
outbrief meeting. Radar coverage is excellent and it appears we will get
all (and then some) we requested in our Air Traffic Requirements document.
Commissioning Flight Check is scheduled to take place June 8, 9 and 10th.
The DVG Switch is scheduled to arrive on June 24th. We should receive the
CENRAP Switch in mid to late July and the new software should be completed
before that time. If all holds true, we may commence ORD in late July.
May 22, 2004
The DD-250 was signed last week and the
FAA AOS Optimazation Team is at the ERI ASR-11 and working their magic on the
radar. I visited the site last week and the radar coverage I witnessed was
excellent. I spent sometime on the phone with a controller in the TRACON
comparing data on both systems.
The problems with the MRSM (PARROT) seem to have been taken care of with a new MRSM.
It appears the FAA Flight Inspection of the ERI ASR-11 is on schedule for June 7-9th, depending on weather. If all goes well, we may be ready to start Operational Readiness Demonstration (ORD) in mid to late July... depending on the delivery date for the DVG Switch and CENRAP Switch. The newly designed antenna ladder will be deployed ASAP. PBI and BOI get the first two ladders, then BGR, then ERI.
Update 12_9_2003
The VDCU evaluation at SCK went well. The
Article 48 Workgroup was pleased with the modifications to the alarm mechanism
and the way the equipment is configured to work.
August_31_2003
The Article 48 Team just finished a review of the revised Radar Control Panel in
Stockton, CA. The panel will be further evaluated in PBI Sept 9th by
representatives of the IOT&E and Article 48 Team. As a member of the
Article 48 Team, I will attend the eval. We will also be discussing any
issues that arose in the PBI transition from analog to digital radar.
Controllers at Boise, ID (BOI) completed evaluation of the newly revised ASR-11
CBI course.
July_31_2003
IOT&E is complete at PBI. The IOT&E downbriefs were held at FAA
HQ on July 15-16. There was a major problem with LAN B on the PBI
ASR-11. A malfunction had the video maps shifting up to 90 degrees from
the norm. This prompted the Raytheon and FAA Team to recreate the problem
in the lab and the team is working at the SCK "Shadow TRACON" and have
identified the problem as a bus failure on LAN B. The bus is hardwired on
the LAN A motherboard but a plug-in on LAN B. They report they have fixed
the LAN B problem but must conduct required testing on the new component.
Another item identified by the IOT&E Team was the number of nuisance alarms on the Radar Control Panel (RCP) and alarms requiring acknowledgment by all RCPs. This had been reported several times by the Article 48 Workgroup. These problems are being addressed by the Article 48 Workgroup. An RCP Telcon will take place next week.
An area west of PBI to 20 NM west on/near the 9L/R final approach is producing false plots/track creating additional workload with traffic calls. A rag map is being formulated to address this problem.
Several other items identified by IOT&E are being "pursued with vigor" by the FAA National ASR-11 Team.
The In-Service Decision has not been made yet due to these pending issues.
The final version of the ASR-11 CBI Training CD should be coming out soon. Most all of the suggested changes should be incorporated into this version. The national plan is for the CBI to be administered as the operation of the ASR-11 nears 45 days before IOC. Classroom and hands-on training will be included. Training for each CPC will be 8 hours.
June_1_2003
West Palm Beach went IOC on May 28th. Perry Doggrell, Jim Green and Andy Chalot from NATCA Article 48 were present when the transition occurred. The target channel performed very well... coverage was much better than their ASR-8, false targets/plots were very scarce and the overall controller transition was smooth. Weather was plentiful and the weather channel was very good with one exception. Some levels of weather did not seem to correspond with TDWR or pilot reports of weather intensity. The levels displayed appeared to be one level under reported conditions (i.e.: level 2 vs. level 3). The TDWR is a more specialized radar... it utilizes a much smaller beam - 1/4 km vs. the ASR-11's 1/2 mile beam, slower rotation and capable of scanning horizontal and vertical. The TDWR antenna is 10 miles west of the ASR-11 antenna. This issue is still being addressed.
Tom Skahen, PBI ASR-11 Local Rep (and member of national IOT&E Team) was charged with the controller preparation and did a splendid job.
IOT&E will take place this month.
The final version of the ASR-11 CBI training was evaluated at PHX on May 20th and is now ready for prime time. It should arrive at a facility near you in the near future.
April_20_2003
ASR11
OT&E at
The NATCA OT&E
team (along with the Agency) conducted an evaluation of the Stockton ASR11 from
Our work group also identified a training issue with setting up the displays. While the scope setup is covered in the ASR11 CBI training course, our work group still found it difficult to quickly set up the radar scope. The knobs on the radar scope all have different functions than they did when the scope was used with an analog (ASR7 or 8) radar. After practicing several times, we were better able to set the scope up. Our concern is that for most facilities, there will not be a lot of practice time, unless the facility has a separate set of displays set up for use/practice with the ASR11. Most facilities will not have this capability. We felt that each facility when transitioning to the ASR11 should have a rover or rovers available who are familiar with the ASR11/radar display setup to assist the facility over the first few days of ASR11 operation.
The Agency also told us about a new improved primary radar processor (ASDP – Advanced Signal Data Processor) that they are currently researching for the ASR11. They feel that the ASDP would give the ASR11’s primary radar more capability to both reduce false targets even further while improving the primary target tracking.
It is my recommendation that a written agreement with the Agency be pursued by NATCA to ensure they continue to fund research and development of the ASDP as well as incorporating the agreed on changes to the RCP.
Perry
Doggrell
NATCA ASR11 Representative
SYSTEM DELIVERY |
2_5_2004 ASR-11 Waterfall (2-5-2004)
The FAA
was slated
to receive 112 DASR systems (Site Locations)
; however, FAA funding has places several sites off the currently funded list.
ERI
11.4.2004
Raytheon, FAA and
local AF are still working the issues that need cleaned up before we commission
the ASR-11. A new ARTS build should be here anyday and that should have
every item cleaned up in the automation arena. The radar performance is
splendid; however, the weather radar seems to be off from what other radar
sources (NEXRAD, Doppler, airborne radars) are showing. The ASR-11 weather
radar shows only quantity of precipitation in weather and the levels are graded
by that amount. We have had several thunderstorms pass through lately and
the ASR-11 is only showing level 1 and 2 weather activity.
10.4.2004
We still have a few issues that need
rectified before we commission the ASR-11. The
commercial power, supplied by Penelec, has been a recurring problem as the feed
has been dropping almost daily and is consistently running about 10 volts low.
This condition causes the UPS to take over and then brings the EG (Engine
Generator) online to provide critical power to the radar until acceptable
commercial power is restored to the system.
Since August 16th, the ASR-11 EG has run over 65 hours.
Penelec has installed monitors at the site but will not talk to anyone
locally. This constant utilization
of the EG and UPS will have an effect on the lifespan of these
vital support pieces. Raytheon
is working the issue and hopes to work out a suitable remedy.
The control tower VDCU (Video Display Control Unit) is not currently backed up
by a UPS. Whenever there is a power
bump (surge or drop) the unit ceases working and a manual reset is required to
get it back in operation. The tower
VDCU controls the display of the ASR-11 weather and primary target selection.
The ARTS IIE MSAW and acquire/drop areas are slightly out of sync and are in the
progress of being amended with a new patch.
Raytheon had a new survey done and now everyone should be on the same
sheet of music.
9.1.2004
The ORD period to date has gone quite
well. We have a few items that are being addressed. Weather radar
levels are off slightly and the ARTS IIE automation is being fine tuned.
Tweaking will continue until the system is like a Swiss-watch. Will keep
you all updated.
8.23.2004
It has been a LONG time coming but I am
ecstatic to announce that the Erie DASR-11 commenced the Operational Readiness
Demonstration (ORD)at 6:00 AM this morning. Thanks to the dedication of a
large group of technicians and experts who worked endlessly throughout the
preceding weekend, this ORD date was struck!! Throughout the day, the
ASR-11 performed as advertised. The ORD will continue until controllers
and technicians are satisfied with the performance and recommend commissioning
the radar. This could transpire in 30 days depending on the radar.
8.17.2004
On the early morning of August 12th, Erie
Tower was a hotbed of activity. The "Dry Run Cutover" test of
the ERI ASR-11 was scheduled and went exceptionally well. Also tested was
the automation interface -flawless. The CENRAP Switch worked as
advertised. CENRAP Plus was also tested an it also passed the
muster. There is still much to be completed before the ORD date of
August 23rd. All Teams (FAA, Raytheon, Contractors, FAA ANI Team and
Airways Facilities (both SMO and local techs) are putting out 110% trying to
meet the August 23rd ORD date. We are all sleeping with our fingers
crossed to make this date happen.
8.6.2004
Well we are about ready to "rock and
Roll" with the ASR-11. Most of the outstanding items have been fixed
or will be before going ORD. ORD date is planned for August 23.
Controller training is in progress. A dry-run cutover will take place
during the midnight shift on August 11-12.
6.12.2004
The FAA ASR-11 Commissioning Flight
Evaluation took place June 8-9 with a KingAir 300 flying the run. Coverage
was excellent in all quadrants with the exception of the Jamestown, NY (JHW)
area and the coverage was much better than our curent ASR-7 provides but not
quite up to that observed by the FAA Optimization Team. The "flight
check" is performed with only 7 of 8 power amplifier modules and in the
Circular Polarization (CP) mode, so this may have had some bearing on the
results. Edge of scope is 59 NM and we observed the BE30 go off the scope
SW thru NW at 2,000 MSL. We lost the target at 16NM on the
ASR-7!!
Aylmer VOR (YQO) was 3,000. JARVS, MOAWK and BROTO intersections were
2,000. Dunkirk (DKK) was 3,000. JHW airport was 4,500 and the JHW
VOR was 5,000 MSL. Tiduote VOR (TDT) was 4,500 and Franklin VOR (FKL)
was 5,000. Corry-Lawrence airport (8G2) was 3,500 and Brokenstraw airport
(PA11) was 4,000 MSL. Port Meadville airport (GKJ) was 3,000...
LINES intersection was 2,500... CLERI intxn was 2,500. These altitudes
were our required altitudes and lower altitudes were not checked at this time so
coverage could and probably will be better than that attained in the flight
check.
The technician/evaluators were going out to the ASR-11 site to compile the results and see if there was anything that could be affecting the JHW area coverage other than the reduced power used for the evaluation.
5.31.2004
Radar
coverage altitudes listed below (Primary Radar / Secondary Radar) were better
that requested and are projected to be as follows:
ERI
Arpt - 700/800
JFN/HZY - 1200/1300
8G2 Arpt - 2300/2600
TDT VOR- 3300/3500
JHW Arpt - 3200/4800
JHW VOR - 3300/4800
The
only problem encountered during optimization was one that has existed for some
time = false plots and false tracks along the outer edge of weather and along
the edges of the different weather levels. The ASR-11 has a "velocity editor" which eliminates
primary targets less than 40kts airspeed. The
AOS Team upped the speed to 60 kts and the situation was vastly improved;
however, we have a problem with increasing to this speed.
We do have non-transponder aircraft that frequent ERI that will be edited
out due to low performance (60 kts or less) and when the wind is strong on
final. Some of these targets
produced by this weather edge phenomena are high-confidence targets and will
give us a "diamond" on the ARTS which indicates a primary target.
This problem is indemic to the system and is being worked on by Raytheon.
2.15.2004
SAT-2 is
complete with the exception of one component (DVG Switch) that has yet arrive at
the ERI site. Progress is good and the system is being reported as
having "some of the best numbers of any system installed to
date." The radar could be on the controller's displays as soon as
late April-early May. The official commissioning will take place in
August. Controller training should commence very soon.
1.13.2004
Site Acceptance Testing (SAT) phase One
was completed last week. This was a basic overview of the entire facility
and went very well. They are now conducting dry-run tests for the eventual
cut-over to ASR-11 data. SAT-2 will commence in the near future. As
soon the FAA reprioritization of the top 5 sites (Fresno, boise, Lincoln, Erie
and Bangor) is completed, timelines will be dictated. We should know
in a couple weeks. During SAT-2 there will be a quite extensive FAA Flight
Check of the radar to ensure that all radar coverage needs are met with the
system. Optimization will take place then and soon after the ASR-11 radar data
will be in use at ERI TRACON.
The ASR-11 Cutover Meeting took place today. Schematics and generic
schedules were reviewed and the items that are germane to ERI were reviewed and
discussed. As stated above, we are not sure yet when cutover will take
place. The lions share of the cutover work will take place from midnight
to 6:00 AM while the tower is closed.
12.17.2003
Part 1 of the ERI ASR-11 Site Acceptance
Testing (SAT) has commenced. This is a five day process and is
basically a final review of the site construction to verify the facility
performs to system specifications. Part 2 is approximately a 10 day
process performing a final test of the ASR-11 system, data collection and
verifying that all items identified in earlier testing have been addressed.
SAT will include a formal flight inspection with a dedicated aircraft and an evaluation of all identified air traffic coverage requirements. The Radar SAT is the final testing of the radar equipment. When Radar SAT has been completed the radar system is at a level of operation that the System Acceptance process can begin.
11.28.2003
The Digital Video Map generator for the
ASR-11 spare radar scope has arrived. A small problem now is the video
maps were created using 9 degrees variation and all surrounding approach
controls and centers are using 8 degrees. This will create an ambiguity
problem on interface operations with these facilities. The problem has
been identified and is being worked at FAA HQ level at this time.
11.3.2003
The safety retrofits for Erie will
commence early December and should be complete within 2-3 weeks. SAT will
recommence when they are complete. The new proposed operational time frame
for ERI to go operational is Apr-May 2004. A new waterfall should be
coming out soon to take into account the safety retrofits and is supposed to be
more realistic in timeframe.
10.17.2003
Safety enhancements for technicians
working on the antenna have been mandated for the ASR-11 now and will be
accomplished prior to continuing SAT. ERI dates are now listed as "To
Be Determined". I will report when this condition changes.
9.22.2003
The requirement for an environmental
cabinet (which has yet to be delivered) for the MRSM installation has
entailed another delay in the operational date of the ASR-11. The "new" proposed date of operation is February 23, 2004.
8.31.2003
The installation of the MRSM has further delayed the start
of SAT. The proposed date for the commissioning of the ERI ASR-11 is now December
17, 2003.
7.31.2003
Site Acceptance Testing (SAT) for facility and construction has
been delayed until September due to the delay in installation of the
MRSM (PARROT).
SAT-2 for radar and electronics will start after SAT-1
completion.
Full
diversity telecommunication microwave
equipment is being pursued at this
time.
The proposed radio tower near the ASR-11 antenna is being
addressed by FAA/Raytheon environmental and legal people. Screen analysis data
is in and RF analysis should be done soon to see the effect of a tower on
theASR-11.
Commissioning should take place in the October/November time frame.
6.1.2003
ERI
is approved for full communications diversity. Leased microwave equipment is being pursued at this time.
Site
Acceptance Testing (SAT) for facility and construction will start early
July. SAT-2 for radar and electronics will start after SAT-1
completion. MRSM (PARROT) relocation is still in the process, we should
have an update soon.
The
proposed radio tower near the ASR-11 antenna is being addressed by FAA/Raytheon
environmental and legal people. Screen
analysis data is in and RF analysis should be done soon to see the effect of a
tower on the ASR-11.
ERI
will have to update the SATP design when the decision is made on the location of
the VDCUs.
The
ASR-11 Flight Check will take place in August.
Commissioning
should take place as early as mid-Sept to October
3.1.2003 With pressure, Raytheon fielded an INCO Team within two weeks and ERI lost no time. The temporary frequency is being used and progress is good. The sail is turning now and the October commissioning date still looks feasible.
1.12.2003 The Erie ASR-11 Raytheon Team will be gone from Erie by January 30th. It seems the Installation and Checkout (INCO) Team who were supposed to be be here installing the wave guide but, did not show. Investigation revealed that Raytheon had failed to order the radar frequency crystals in time for their manufacture to avail the scheduled INCO start. It takes around 6 months to grow the crystals. The FAA and Raytheon are now attempting to select a temporary frequency from the available crystals for a new frequency close to Erie's ASR-11 assigned frequency that will not interfere with the existing ERI ASR-7 radar. This will (hopefully) be completed soon and the INCO can proceed with the temporary frequency until the new crystals are delivered. Word is that Raytheon is putting together a new INCO Team which will be at ERI hopefully in early February. We are still hoping to make the October 2003 commissioning date.
ROA
3.1.2003
The Kick-Off Meeting
at ROA was on
February 25th. They will now be reviewing other candidaate sites for the
ASR-11 antenna. FAA HQ has agreed to attempt to pursue a means of
increasing radar coverage in the higher elevations which is blocked by the
nearby mountains. This will be a moot point
when STARS is installed as the ability to mosaic in other
radar systems will solve the problem
NXX/PHL
PHL is operational with ASR-11 (NXX Site) with STARS interface. (March 6, 2003)
2.20.2003Update
2_21_2003
The NATCA
ASR-11 OT&E Team completed a two week Air Traffic User Evaluation at ACY and
PHL on the Navy Willow Grove (NXX) ASR-11. The evaluation was for
the STARS Interface at PHL. The team had some reservations about the
ASR-11 primary radar performance in the presence of weather and in the
transitional phases of different levels of weather. The ASR-11 velocity
editor was set at 60 kts for this evaluation, as STARS utilizes a velocity
editor set at 60 kts also. Given the STARS utilization of numerous radar
sites, the team approved the ASR-11 site for operational activation at PHL.
PHL plans to go IOC on March 6, 2003.
history:
Site Acceptance Test (SAT) completed 10/2/02
ANI revisits site 1/27/03
OT&E activities 3/3/03
Technical Performance Records Start Date 2/3/03 - completed 2/7/03
Commissioning Flight Check - 2/10/03 - completed 2/12/03
Partial Joint Acceptance Inspection (JAI) - 3/5/03
IOC in support of PHL STARS - 3/6/03
Commissioning 8/15/03
RME
->
Design and construction of ASR-11 facility on hold. Decision needed to
determine if this site is still valid.
-> Lease is highly recommended to protect the preferred site.
MMU
-> 8/20/02 Downselect Telcon resulted in Sites 3, 5, 13 and 15 as candidate sites
for further analysis.
-> Rights of Entry (ROE) for sites 3, 5 and 15 are in place. ROE for site 13 is
undergoing legal review.
-> Pending approval of site 13, Raytheon will submit a Preliminary Site Survey
Report (PSSR) based on panoramics and analysis of the 4 candidate sites.
ABE
-> Site 14 was selected as the preferred site.
-> Legal Description Site Visit - 10/22/02
AVP
-> Preliminary Site Survey Report (PSSR) Submittal - 11/21/02
CRW
-> Kickoff Site Survey Meeting - 12/3/02
RDG
-> Kickoff Site Survey Meeting - 10/22/02
HTS
-> Site Survey NLT Start date - August '03
CKB
->Site Survey NLT Start date - January '04
BGM
->Site Survey NLT Start date - March '04
ELM
-> Site Survey NLT Start date - April '04
e-Mail to
Perry Doggrell
Available Links to DASR Systems
| Raytheon ASR-11 FAA's ASR-11 Site |
| Northrop Grumman
ASR-12 |
Visitors since 9/8/2002
Home | Safety | Political | Monthly Safety Report | Privatize | STARS
Last Update 11/4/2004